Papanastasiou Fly-Over
The construction time was 2 months before being completed and given to the public for use. From the pedestals, a special mold was manufactured within one day.
The body was prestresed in 4 steps and with special additives, the team could perform tension every 4 days. The most important issue of all was the 4th step, as there was circulation in the national highway due to the high touristic season during the time of construction. We used a system with metal stretcher that could securely allow the drivers and workers to move.
At the same time, it can take «DOKA» on it and provide safety to the workers.